static Aspose::Tasks::Key< Aspose::Tasks::CostAccrualType, Aspose::Tasks::RscKey > & | AccrueAt () |
| Determines how and when resource standard and overtime costs are to be charged, or accrued, to the cost of a task. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | ActiveDirectoryGuid () |
| The Active Directory Guid for a resource. More...
|
|
static Aspose::Tasks::Key< System::Decimal, Aspose::Tasks::RscKey > & | ActualCost () |
| Costs incurred for work already performed by resources on their tasks, along with any other recorded costs associated with the task. More...
|
|
static Aspose::Tasks::Key< System::Decimal, Aspose::Tasks::RscKey > & | ActualOvertimeCost () |
| Costs incurred for overtime work already performed on tasks by assigned resources. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::Duration, Aspose::Tasks::RscKey > & | ActualOvertimeWork () |
| The actual amount of overtime work already performed by resource assigned to tasks. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::Duration, Aspose::Tasks::RscKey > & | ActualOvertimeWorkProtected () |
| The amount of work through which actual overtime work is protected. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::Duration, Aspose::Tasks::RscKey > & | ActualWork () |
| The amount of work that has already been done by resource assigned to tasks. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::Duration, Aspose::Tasks::RscKey > & | ActualWorkProtected () |
| The amount of work through which actual work is protected. More...
|
|
static Aspose::Tasks::Key< double, Aspose::Tasks::RscKey > & | ACWP () |
| The actual cost of a work performed by a resource for the project to-date. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | AssignmentOwner () |
| The name of an assignment owner. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | AssignmentOwnerGuid () |
| The GUID of an assignment owner. More...
|
|
static Aspose::Tasks::Key< System::DateTime, Aspose::Tasks::RscKey > & | AvailableFrom () |
| The starting date that a resource is available for work at the units specified for the current time period. More...
|
|
static Aspose::Tasks::Key< System::DateTime, Aspose::Tasks::RscKey > & | AvailableTo () |
| The end date that a resource is available for work at the units specified for the current time period. More...
|
|
static Aspose::Tasks::Key< double, Aspose::Tasks::RscKey > & | BCWP () |
| The budgeted cost of a work performed by a resource for the project to-date. More...
|
|
static Aspose::Tasks::Key< double, Aspose::Tasks::RscKey > & | BCWS () |
| The budget cost of a work scheduled for a resource. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::BookingType, Aspose::Tasks::RscKey > & | BookingType () |
| The booking type of a resource. More...
|
|
static Aspose::Tasks::Key< System::Decimal, Aspose::Tasks::RscKey > & | BudgetCost () |
| Budget costs for budget cost resources. Budget resources are assigned only to the project summary task. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::Duration, Aspose::Tasks::RscKey > & | BudgetWork () |
| budget work for budget work and material resources. Budget resources are assigned only to the project summary task. More...
|
|
static Aspose::Tasks::Key< System::SharedPtr< Aspose::Tasks::Calendar >, Aspose::Tasks::RscKey > & | Calendar () |
| The calendar of a resource. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::NullableBool, Aspose::Tasks::RscKey > & | CanLevel () |
| Determines whether resource leveling can be done on a resource. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | Code () |
| The code or other information about a resource. More...
|
|
static Aspose::Tasks::Key< System::Decimal, Aspose::Tasks::RscKey > & | Cost () |
| The total scheduled or projected cost for a resource, based on costs already incurred for work performed by resources assigned to the tasks, in addition to the costs planned for the remaining work. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | CostCenter () |
| Indicates which cost center the costs accrued by the resource should be charged to. More...
|
|
static Aspose::Tasks::Key< System::Decimal, Aspose::Tasks::RscKey > & | CostPerUse () |
| The cost that accrues every time that a resource is used. More...
|
|
static Aspose::Tasks::Key< double, Aspose::Tasks::RscKey > & | CostVariance () |
| The difference between the baseline cost and total cost for a resource. More...
|
|
static Aspose::Tasks::Key< System::DateTime, Aspose::Tasks::RscKey > & | Created () |
| The date and time when a resource was added to the project. More...
|
|
static Aspose::Tasks::Key< double, Aspose::Tasks::RscKey > & | CV () |
| The earned value cost variance, through the project status date. CV is the difference between the task's BCWP (budgeted cost of work performed) and ACWP (actual cost of work performed). More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | EMailAddress () |
| The email address of a resource. More...
|
|
static Aspose::Tasks::Key< System::DateTime, Aspose::Tasks::RscKey > & | Finish () |
| The date when a resource is scheduled to complete work on all assigned tasks. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | Group () |
| The group to which a resource belongs. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | Guid () |
| Contains the generated unique identification code for the resource. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | Hyperlink () |
| The title or explanatory text of a hyperlink associated with a resource. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | HyperlinkAddress () |
| The address for a hyperlink associated with a resource. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | HyperlinkSubAddress () |
| The specific location in a document in a hyperlink associated with a task. More...
|
|
static Aspose::Tasks::Key< int32_t, Aspose::Tasks::RscKey > & | Id () |
| The position identifier of a resource within the list of resources. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::NullableBool, Aspose::Tasks::RscKey > & | Inactive () |
| Determines whether a resource was made inactive by a user who has administrative rights. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | Initials () |
| The initials of a resource. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::NullableBool, Aspose::Tasks::RscKey > & | IsBudget () |
| Determines whether a work, material, or cost resource is a budget resource. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::NullableBool, Aspose::Tasks::RscKey > & | IsCostResource () |
| Determines whether a resource is a cost resource. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::NullableBool, Aspose::Tasks::RscKey > & | IsEnterprise () |
| Shows whether a resource is from the enterprise resource pool (true) or the local resource pool (false). More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::NullableBool, Aspose::Tasks::RscKey > & | IsGeneric () |
| Determines whether a resource is generic or not. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::NullableBool, Aspose::Tasks::RscKey > & | IsNull () |
| Determines whether a resource is null. More...
|
|
static Aspose::Tasks::Key< bool, Aspose::Tasks::RscKey > & | IsTeamAssignmentPool () |
| Shows whether the current resource is a team resource. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | MaterialLabel () |
| The unit of measure for the material resource. More...
|
|
static Aspose::Tasks::Key< double, Aspose::Tasks::RscKey > & | MaxUnits () |
| The maximum number of units representing the maximum capacity for which a resource is available to accomplish any tasks during the current time period. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | Name () |
| The name of a resource. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | NotesRTF () |
| The text notes in RTF format. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | NotesText () |
| Notes' plain text extracted from RTF data. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::NullableBool, Aspose::Tasks::RscKey > & | Overallocated () |
| Indicates whether a resource is assigned to more work on a specific task or all tasks than can be completed within normal working capacity. More...
|
|
static Aspose::Tasks::Key< System::Decimal, Aspose::Tasks::RscKey > & | OvertimeCost () |
| The total overtime cost for a resource on all assigned tasks. More...
|
|
static Aspose::Tasks::Key< System::Decimal, Aspose::Tasks::RscKey > & | OvertimeRate () |
| The rate of pay for overtime work performed by a resource. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::RateFormatType, Aspose::Tasks::RscKey > & | OvertimeRateFormat () |
| The units used by Microsoft Project to display the overtime rate. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::Duration, Aspose::Tasks::RscKey > & | OvertimeWork () |
| The amount of overtime scheduled to be performed by a resource on a task and charged at the overtime rates of the resources involved. More...
|
|
static Aspose::Tasks::Key< double, Aspose::Tasks::RscKey > & | PeakUnits () |
| The maximum assignment unit for a resource at any one point in time for all tasks to which the resource is assigned. More...
|
|
static Aspose::Tasks::Key< int32_t, Aspose::Tasks::RscKey > & | PercentWorkComplete () |
| The percentage of work completed across all tasks. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | Phonetics () |
| The phonetic spelling of the resource name. For use with Japanese only. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::Duration, Aspose::Tasks::RscKey > & | RegularWork () |
| The total amount of non overtime work scheduled to be performed by resource. More...
|
|
static Aspose::Tasks::Key< System::Decimal, Aspose::Tasks::RscKey > & | RemainingCost () |
| The remaining scheduled expense that will be incurred in completing the remaining scheduled work. More...
|
|
static Aspose::Tasks::Key< System::Decimal, Aspose::Tasks::RscKey > & | RemainingOvertimeCost () |
| The remaining scheduled overtime expense for a resource. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::Duration, Aspose::Tasks::RscKey > & | RemainingOvertimeWork () |
| The amount of remaining scheduled overtime. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::Duration, Aspose::Tasks::RscKey > & | RemainingWork () |
| The time still required to complete a task or set of tasks. More...
|
|
static Aspose::Tasks::Key< System::Decimal, Aspose::Tasks::RscKey > & | StandardRate () |
| The rate of pay for regular, non-overtime work performed by a resource. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::RateFormatType, Aspose::Tasks::RscKey > & | StandardRateFormat () |
| The units used by Microsoft Project to display the standard rate. More...
|
|
static Aspose::Tasks::Key< System::DateTime, Aspose::Tasks::RscKey > & | Start () |
| The date when an assigned resource is scheduled to begin working on a task. More...
|
|
static Aspose::Tasks::Key< double, Aspose::Tasks::RscKey > & | SV () |
| The earned value schedule variance, through the project status date. SV is the difference between budgeted cost of work performed (BCWP) and budgeted cost of work scheduled (BCWS). More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::ResourceType, Aspose::Tasks::RscKey > & | Type () |
| The type of a resource. More...
|
|
static Aspose::Tasks::Key< int32_t, Aspose::Tasks::RscKey > & | Uid () |
| The unique identifier of a resource. More...
|
|
static Aspose::Tasks::Key< System::String, Aspose::Tasks::RscKey > & | WindowsUserAccount () |
| The NT account associated with a resource. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::Duration, Aspose::Tasks::RscKey > & | Work () |
| The total amount of time scheduled for a resource on a task. More...
|
|
static Aspose::Tasks::Key< Aspose::Tasks::WorkGroupType, Aspose::Tasks::RscKey > & | Workgroup () |
| The type of a workgroup to which a resource belongs. More...
|
|
static Aspose::Tasks::Key< double, Aspose::Tasks::RscKey > & | WorkVariance () |
| The difference between baseline work of a resource and the currently scheduled work. More...
|
|